Power - On and Off
Power supply has been playing cat and
mouse for quite sometime for the last two months. Constant blaming of nature's
vagaries since ages is a reprehensible excuse. Acute shortage of man and
material adds to the woes.
By Zubair Ahmed
If you ask why so many interruptions in power
supply now, they blame it on the unexpected pre-monsoon showers. The rain was a
relief from scarcity of water and the simmering heat. But it brought miseries
of a different kind. Nights had turned nightmares without power. The
authorities still feel the unexpected rain was the spoiler, the usual rhetoric
though. Its a fact reiterated time and
again that rain and power cannot co-exist peacefully in our territory. Vagaries
of the nature have been an reprehensible excuse since ages. But, the overall
power situation in South Andaman had gone for a toss since February this year. During
last two months, that too during Board exams, power played cat and mouse.
And why is it so in Port Blair too, where the
vegetation is low and with so many feeders? They blame it on relay
coordination. Oops.. its the new term doing rounds. Or maybe that is what we
are told to believe. The supply from different small and big power plants with
different DG sets and calibrations is in itself a problem, if not properly
coordinated.
Speaking with Andaman Chronicle, Mr U K Paul, SE,
Electricity Department said that he is expecting a consultancy team from
Chennai, who will do the survey and properly set right the relay coordination.
And he is hopeful that once its done, frequent tripping of Gensets will come
down reducing the downtime.
The power generation scenario in South Andaman is
also not very comfortable after IPP Suryachakra Power Corporation Ltd shut down
one more 5 MW Genset from its installed capacity of 20 MW. Its generating 10 MW
power now. The other two Hired Power Plants (HPP) - Sudhir Ready and New Bharat
contributes around 14 MW. In fact, New Bharat, which was almost written off was
coaxed to run their gensets. IPP and HPPs seems to have turned constant pain in
the neck for the Administration.
The department run power plants at Phoenix Bay
and Chatham
generates 15.8 MW. The newly installed 5 MW Genset is the only saving grace as
of now. Any further disruption by IPP or HPPs would plunge the territory into
darkness.
The Transmission and Distribution is one sector,
where the Department has been drawing flak from all quarters. Even when power
was surplus, the frequent interruptions due to poor maintenance and obsolete
and worn out infrastructure had marred the reputation of the department. It
forced the Administration to conduct an audit of power generation as well as
transmission and distribution. The report saw light in November last year. Six
months are over, and as mentioned in the report, most of the short-term work
would be completed within two years.
Moreover, lack of inter-departmental coordination
is quite obvious when it comes to proper maintenance of overhead as well as UG
cables. The Electricity authorities blame the Forest Department for not giving
sufficient corridor for laying power lines. In fact they rue the strenuous and
tedious process of clearances.
The proposal to replace the overhead bare
conductors with insulated cables in the Rural areas is yet to begin, and this
rainy season too, blame would be on monsoon miseries. A 33 KV sea-link line
Zebra- and Zebra-2 between Surya Chakra Power Plant at Bambooflat and Chatham
Power House is completed which would help in power evacuation as well as
optimal use of grid apart from the two line Panther-1 and Panther-2 connecting
SPCL with Port Blair at Garacharma Sub-Station.
The ground staff of the department is seen working
very hard, clearing vegetation, changing fuse, pruning branches of trees and
their efforts are well appreciated by everyone, including the Administrator.
But, what is seen is not what actually would have been the situation. There is
acute shortage of man and material in the department. There are more than 65
posts of linemen lying vacant for decades now. There is shortage of JEs as
well. The lines are now maintained by untrained mazdoors, and any accident
would attract huge hue and cry. The department is run by skeletal staff and its
quite visible in all site offices. There is no efforts to fill up the posts,
which is one main reason in delivery of services. Many gensets in the department-run power
plants are performing sub-optimal just for want of spare parts. The list of
excuses for all shortfall in service can be attributed to shortage of manpower
as well as material.
The Panel - 5 which covered a large area from Hope
Town to Shoal Bay and Jirkatang with a peak
requirement of 3 MW has been bifurcated with installation of a new sub-station
at Bambooflat. Panel 5 has been branched off into three feeders - Feeder 1
-Hope Town, Feeder 2 - Shoal
Bay and Jirkatang
combined. Up to Wimberly Gunj, the UG cable is connected to SPCL directly. And,
the sub-station which was due for last three years have started functioning on
trial basis from last Saturday. There are a few hiccups, which needs to be
overcome. But, it doesn't seem to be a major solution as the feeder which
caters Shoal Bay and Jirkatang - two ends - is
overhead line from Bambooflat to these areas. Any disruption in Shoal Bay
would still effect Jirkatang and vice-versa. Only safe zone, as informed by the
concerned authorities is up to Wimberly Gunj, which has been separated from
Jirkatanag and Shoal
Bay line. Ideally, a
sub-station anywhere close to Wimberly Gunj would be the long term solution
with three different feeders catering in three different directions.
There is a mention of more sub-stations in the
audit report. That seems to be the only solution in the long run. As the thumb
rule, 33KV line should not go beyond 20 kms without a sub-station at every 20
kms.
"A survey needs to be conducted to assess the
requirement of sub-stations throughout the territory, which needs to be taken
up urgently," U K Paul said.
The 5-MW Solar Plant as of now is more a problem
than a solution with huge cloud movements throughout the year. The peak
generation that too upto 3 MW during sunny days is hardly for 15-30 minutes
between 11.45 am to 12.15 pm. And the sudden fluctuation affects the whole grid
with pressure on other power plants. Roof-top solar panels is a good solution
for individual houses, but the project is taking its own sweet time.
The 30-MW proposed LNG plant is still in MOU stage,
and it seems to be one solution in the field of clean power generation. But if
overhauling of transmission and distribution is deferred, nothing is going to help
improve the situation.
All talks of renewable energy is quite welcome and
needs appreciation. But, in a territory like Andamans, the base load cannot be
left to the nature to decide, and hence diesel gensets are going to stay, and a
focused vision with long-term planning is required well in advance. Or else, if
we keep adding one or two small gensets every now and then on piecemeal basis,
we will be accumulating more problems of diverse nature.
Disclaimer: I regret that lack of flow in this
article is due to four or more power interruptions experienced in one hour.
No comments:
Post a Comment